Scheduling projects incorporated with materials ordering results in a more realistic
problem. This paper deals with the combined problem of project scheduling and material ordering. The
purpose of this paper is to minimize the total cost of this problem by determining the optimal values
of activity duration, activity nish time and the material ordering schedule subject to constraints. We
employ a genetic algorithm approach to solve it. Elements of the algorithm, such as chromosome
structure, untness function, crossover, mutation and local search operations are explained. The results
of the experimentation are quite satisfactory.
Hassanzadeh, F., Sheikh Sajadieh, M., & Shadrokh, S. (2009). Concurrent Project Scheduling and Material Planning: A Genetic Algorithm Approach. Scientia Iranica, 16(2), -.
MLA
F. Hassanzadeh; M. Sheikh Sajadieh; S. Shadrokh. "Concurrent Project Scheduling and Material Planning: A Genetic Algorithm Approach". Scientia Iranica, 16, 2, 2009, -.
HARVARD
Hassanzadeh, F., Sheikh Sajadieh, M., Shadrokh, S. (2009). 'Concurrent Project Scheduling and Material Planning: A Genetic Algorithm Approach', Scientia Iranica, 16(2), pp. -.
VANCOUVER
Hassanzadeh, F., Sheikh Sajadieh, M., Shadrokh, S. Concurrent Project Scheduling and Material Planning: A Genetic Algorithm Approach. Scientia Iranica, 2009; 16(2): -.